Distribution architecture (typical chain)

Utility 10kV HV switchgear Transformer 10kV/0.4kV LV switchgear UPS RPP / PDU IT racks
Large AI data centers often use 2N dual feed. For high-power-density AI zones also consider per-rack PDU capacity and busway selection.

Input parameters

racks
kW/rack
Typical: standard racks 4–8 kW, high-density AI / liquid-cooled 20–100+ kW
%
Servers typically run at 50%–80%; idle units still consume power
1.1 excellent1.52.5 poor
PUE = 1.50
PUE = total data-center power ÷ IT power. Regulations require new large data centers to reach PUE ≤ 1.3
Locating you…
$/kWh
Auto-matched to local commercial average tariff by IP
kgCO≡/kWh
China national grid average ≈ 0.5568 kgCO≡/kWh; adjust per region

Results

Effective IT load
kW
Total data-center power
kW
Annual energy
MWh/yr
Annual electricity cost
/yr
Annual carbon
tCO≡/yr
Cost per rack per year (rack mode)
/rack·yr

Power breakdown (total = 100%)

IT equipment
Cooling (CRAC / tower)
Power distribution losses (UPS/transformer)
Lighting & other
Total power = IT load × PUE
Non-IT part split by typical ratios: cooling ≈ 70%, distribution losses ≈ 25%, lighting & other ≈ 5%

PUE sensitivity (same IT load)

PUE scenarioTotal power kWAnnual energy MWhAnnual cost

UPS & battery quick sizing

Auto-matches mainstream high-power 3-phase UPS and LFP smart lithium battery cabinets from the effective IT load above. Capacities are typical ratings; final selection per vendor manual. UPS capacity already includes redundancy factor and 20% design margin.

UPS capacity needed kVA Battery capacity needed kWh UPS redundancy Battery backup time

High-power 3-phase UPS (IT load, incl. redundancy & margin)

Brand / series
Recommended modelCapacity / unitUnitsTotal capacityFull-load input / unitTotal input powerNote

LFP smart lithium battery cabinets (capacity by backup time)

Brand / series
Recommended modelCapacity / cabinetCabinetsTotal capacityFootprint ref.Note
Same basis as the “Backup Power” page: UPS capacity = IT load ÷ 0.9 × (1 + 20% margin) × redundancy factor (N+1 = 1.25, 2N splits across two buses); battery capacity = IT load × backup hours ÷ 0.94 (UPS efficiency). Unit counts are the minimum integer combination meeting the demand; for small loads pick smaller models and verify modular scalability.

LV switchgear & ATS quick sizing

Auto-matches LV switchgear (main incoming / busbar), smart rack power panels (one per row) and ATS automatic transfer switches (mains/genset) from total power. Capacities are typical ratings; final selection per vendor manual. ATS demand links to genset capacity on the “Backup Power” page.

Total incoming current A RPP needed units ATS switching current A Architecture Racks per row

LV switchgear (main incoming / distribution center)

Cabinet series
Recommended typeMain busbar ratingIncoming setsFeeder boards (ref.)Total incoming currentNote

Smart rack power panels (rack-level distribution)

Brand / series
Recommended modelIncoming ratingUnitsRow load ref.Note

ATS transfer switches (mains ↔ genset)

Brand / series
Recommended modelRated currentUnitsSwitching capacityNote
Basis: total incoming current = total power ÷ 0.9 (apparent kVA) × 1.443 (400V 3-phase); RPP incoming rating by row load current; ATS switching current = genset kVA × 1.443 (ATS must carry full genset output). ATS is a PC-class transfer switch (GB/T 14048.11); in a 2N architecture each bus gets one unit. Feeder board count is an estimate by rack count; final circuits need detailed design.